Station 55 - January Update
 
By MCESD#2 - Montgomery Fire Department
January 27, 2021
 

January update on construction of Station 55 -

Grade beams for fire station are being dug. Concrete pours for the building foundation will be complete in the next few weeks.

The pump is being installed to drain the detention pond.

Major site underground work is being completed with the installation of the water lines and aerobic system.